Under what cost threshold is the use of operating and maintenance (O&M) funds for construction allowed?

Prepare for the USACE Contracting Officer Review Board (CORB) Test. Utilize our quizzes with flashcards and multiple choice questions, each offering helpful hints and explanations. Get ahead in your exam preparation now!

Multiple Choice

Under what cost threshold is the use of operating and maintenance (O&M) funds for construction allowed?

Explanation:
O&M funds can be used for construction only when the project is considered minor and its cost falls within a specific ceiling. The established ceiling is four million dollars or less. This allows small, non-major improvements to be funded from operating funds without tying up MILCON appropriations. If a project would exceed four million, it generally must be funded through MILCON or another appropriate appropriation, not O&M. The other options either set the threshold too low, imply funding is never allowed, or suggest a higher limit than the policy allows.

O&M funds can be used for construction only when the project is considered minor and its cost falls within a specific ceiling. The established ceiling is four million dollars or less. This allows small, non-major improvements to be funded from operating funds without tying up MILCON appropriations. If a project would exceed four million, it generally must be funded through MILCON or another appropriate appropriation, not O&M. The other options either set the threshold too low, imply funding is never allowed, or suggest a higher limit than the policy allows.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy