Which statement correctly describes Progress Payments under FAR 32.104?

Prepare for the USACE Contracting Officer Review Board (CORB) Test. Utilize our quizzes with flashcards and multiple choice questions, each offering helpful hints and explanations. Get ahead in your exam preparation now!

Multiple Choice

Which statement correctly describes Progress Payments under FAR 32.104?

Explanation:
Progress payments under FAR 32.104 are a financing tool that provides payment as work progresses, but the payment is based on costs actually incurred by the contractor to date rather than the value of specific milestones or events. The requirement for an approved accounting system ensures that those costs are tracked and allocated properly, so the government can verify allowability and accuracy before releasing funds. This combination—costs incurred plus an approved cost accounting system—is what makes this option the correct description. Progress payments are not limited to commercial items, and they can be used on production contracts as appropriate, so the other statements don’t fit FAR 32.104.

Progress payments under FAR 32.104 are a financing tool that provides payment as work progresses, but the payment is based on costs actually incurred by the contractor to date rather than the value of specific milestones or events. The requirement for an approved accounting system ensures that those costs are tracked and allocated properly, so the government can verify allowability and accuracy before releasing funds. This combination—costs incurred plus an approved cost accounting system—is what makes this option the correct description. Progress payments are not limited to commercial items, and they can be used on production contracts as appropriate, so the other statements don’t fit FAR 32.104.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy